Customer

New college extension for Post-16 media, health and social care centre comprising sixth form commons rooms, catering facilities and external works.

  • Value: £2,000,000
  • Duration & Dates: 22 Weeks, Dec 2011 – Apr 2012
  • Form of Contract: JCT Design & Build

Key Project Stats

2
Million pounds
22
Weeks

Key deliverables:

  • Working in a ‘live’ college environment
  • Flexible programme to accommodate the college activities and curriculum
  • Installed ground source heat pumps with 15 bore holes 100m deep
  • Installed extensive & detailed external hard and soft landscaping
  • Complete fit out to include IT infrastructure, catering equipment and specialist teaching equipment
  • Completed within time and budget.