Design and Build of a purpose built Sixth Form Centre featuring dedicated teaching rooms, study areas, IT suite, offices and meeting/break out areas.

  • Client: Norton Hill Academy
  • Value: £900,000
  • Duration & Dates: 26 Weeks, Sep 2013 – May 2014
  • Form of Contract: JCT Design & Build

Key Project Stats

2
Storey
10
Classrooms
26
Weeks

Key deliverables:

  • Steel frame construction
  • Curtain walling
  • Working in a ‘live’ school environment
  • Flexible work programme to accommodate activities and curriculum
  • Coordination with local stakeholders on delivery etc
  • Completed on time and within budget.