Design, manufacture and installation of a new accommodation block, comprising of two classrooms and a drama studio to replace the two existing temporary teaching block at the rear of the school. An existing temporary training facility was re-sited within the School grounds.

  • Value: £647k
  • Duration & Dates: 29 weeks. Apr 2014 – Oct 2014
  • Form of Contract: NEC 3 (June 2015)

 

 

Key Project Stats

1
Drama studio
2
Classrooms
29
Weeks

Key deliverables:

  • ‘Live’ school environment
  • Critical programme delivery
  • Gabion basket retaining wall.