Customer

Refurbishment of boarding school accommodation

  • Value: £565,000.00
  • Contract: JCT Intermediate Contract 2016 with amendments
  • Duration: 8 weeks

Refurbishment of the 2nd floor boarding house accommodation, the refurbishment of 24 bedrooms & associated WC facilities carried out in the summer holidays.

The works consisted of the removal of all furniture, walls & ceilings, full mechanical & electrical works, new plaster finishes, new joinery & decoration.

The working area was situated on the 2nd floor, access was gained from the outside via temporary stairs so as not to affect the previous refurbishment, all materials & site staff used this for access daily.